Construction of the 220/110 kV Norki electrical substation
1. The subject of the contract is the construction of the 220/110 Norki substation as part of the project "Interconnection between Poland and Lithuania (currently known as Harmony Link) along with the connection of the Suwałki Special Economic Zone". The scope of work includes design work and construction and assembly works. Furthermore, the Contracting Authority provides for the possibility of exercising options: Option no. 1 (with the possibility of dual application and independently of each other) - equipment of the R220 kV reserve bay, has been described in point 1.2.1 of Part II of the SWZ PFU. Option no. 2 (with the possibility of dual application and independently of eac
Translated automatically from the original language, so check the official notice for the exact wording. Original title: Budowa stacji elektroenergetycznej 220/110 kV Norki