Execution of construction and assembly works for the task: "Construction of GPZ Dźwierzuty"
1. The subject of the order is the construction of the 110/15 kV GPZ Dźwierzuty electrical substation together with technical infrastructure, the construction of a double-circuit 110 kV HV overhead line from pole No. 112 and 113 of the existing 110 kV line relation Olsztyn 1 - Korpele to GPZ Dźwierzuty and the construction of MV cable outlets from GPZ Dźwierzuty. The scope of work includes: • dismantling of the existing PZ Dźwierzuty building • construction of the station building with construction and installation equipment: - AC and DC auxiliary needs cabinets, SOT cabinets, telemechanics cabinets, energy measurement cabinets, protection automation cabinets - devices
Translated automatically from the original language, so check the official notice for the exact wording. Original title: Wykonanie robót budowlano-montażowych dla zadania: „Budowa GPZ Dźwierzuty”