NEW CAMPUS IN HEFFINGEN - Lot 7 Electrical installation works
The start of the works is scheduled for 16.04.2027. The duration of the works is 408 working days. The start of the preparation of workshop drawings is scheduled for 16.04.2027. The duration of the preparation of workshop and assembly drawings and prefabrication works is 37 working days. The start of on-site assembly is scheduled for 10.06.2027. The duration of on-site assembly is 229 working days. The start of commissioning is scheduled for 24.05.2028. The duration of commissioning, acceptance testing, resolution of punch list items and preparation of As-Built drawings is 142 working days